Speeding up Raw Material Movement to Boost Plant Production for a major Japanese Manufacturing company.
Challenge
Problem:
One of the leading manufacturing companies found themselves grappling with a challenging situation: a sudden surge in motor demands by 300% due to a significant increase in orders for MV and HV motors.
When our team had a detailed look, we discovered the movement of raw materials from the warehouse to the plant production line was plagued, resulting in a 20% decrease in overall production.
Solution
CUSMAT's Forklift Simulator
Cusmat’s Last-Mile Delivery Skilling App